Build porch...

back

The next day, seal the roofing material, customized formwork from below, put rebar (I found).


Made the formwork for floor slabs, waterproofing, reinforcement

Poured concrete slab about 5-8 cm, has covered film.


slab

After 3 days, dismantle formwork. Began masonry porch. Deciding to save a little (or rather, had little foam block) masonry led to the quarter-block, 20 cm


begin...

 


see ...

The room is small, clutch goes fast, has already shown a small window, because the wall is thin, mesh reinforcement is placed in 2 row.


see window porch

Want to see next?, click the link "forward"! ...